The Northpoint tavern on Hayley Drive off Mortlake Road has been on the drawing board for 12 years and still remains unfinished.
Carol Altmann – The Terrier
Is this Warrnambool’s ugliest building site?
I had no idea, until last night’s Warrnambool City Council meeting, that the poor residents of Hayley Drive, near Northpoint shopping centre on Mortlake Rd, have been looking at this stunning vista of a half-finished building for years.
In fact the planning process for what was going to be a “licensed restaurant” at the back of the bottle shop started in 2006.
That is four councils ago.
Since then the plan has been back to the council eight times for extensions and amendments and more extensions, as the “licensed restaurant” changed and morphed and popped out at the council meeting last night as the Northpoint Hotel, complete with a bar, a bistro and a TAB.
Some residents have had to object EIGHT times to the same project.
One elderly objector, now aged 89 (she was in Year 12 when the project started…okay, maybe not quite, but you get my point), said she always feared the restaurant would morph into a hotel. It looks like she was absolutely right.
I have come to the highly scientific conclusion that the planning laws – local and state – really suck.
How can a project come back to a council eight times over 14 years? How can a building sit half finished for years?
How can prime old Warrnambool buildings be demolished, and their blocks of land sit empty for years and years as what was an “urgent” project becomes suddenly not so urgent?
And why do the goal posts keep moving, so that a licensed restaurant becomes a hotel?
Cr Sue Cassidy was among the councillors last night who were not happy with that change and moved – successfully as part of the planning approval – that the word “hotel” not be used in any signage.
The goal posts must not keep moving, Cr Cassidy said.
I am personally delighted to hear this, as my little street is about to do a David and Goliath by challenging the whiz bang Lyndoch Medical Clinic that was approved in 2017 , “amended” in February this year and approved again last month.
This “amendment” has seen the project double in size. Cr Cassidy, as we know, is both a director of the Lyndoch Medical Clinic and a Lyndoch board member.
From what Cr Cassidy said last night, it looks like my street can count on her support when it rolls onto VCAT.
That is another whole story, for another day.
Midfield Merrivale milk factory off the boil
How the proposed milk processing factory at Merrivale would have appeared on the skyline near the Warrnambool Showgrounds. Image: Warrnambool City Council.
The Terrier – Carol Altmann
[dropcap style=”font-size: 35px; color: #8cc7d0;”] T [/dropcap]wo of the most controversial projects to be approved in Warrnambool in recent times – the milk processing factory in Merrivale and a nine-storey apartment block on Merri St – have been put on the backburner by their developer, the Midfield Group.
It is now two years since both projects received planning approval, but not much has happened at either site since.
The milk factory was expected to be up and running within 12 to 18 months of being given the green light from an independent planning panel in May 2015.
It is a similar story with the proposed nine-storey apartment block on the corner of Merri and Gillies streets, which – despite arguments to save it – saw the 1940s Madden’s/Sandilands building demolished within weeks after the development was approved in early 2015.
When the planning application was lodged by Tract Consultants, acting on behalf of Baybern Developments/Midfield, it urged the Warrnambool City Council to approve the project as quickly as possible because its client was keen to get started.
The prominent corner block remains vacant and wire fenced, joining the Criterion Hotel site, the former Caltex petrol station on Raglan Parade, and the former Warrnambool gas works near Harris Reserve as “frozen” projects that have sat untouched.
The proposed nine-storey apartment block on the corner of Gilles and Merri streets, Warrnambool. While approved in early 2015, little has happened.
[dropcap style=”font-size: 35px; color: #8cc7d0;”] T [/dropcap]
he Midfield Group and Baybern Developments are owned by one of Warrnambool’s most successful businessmen, Colin McKenna.
A spokesman for Midfield and Baybern, Daniel Aarons, said today that the company’s priorities had changed for both projects since it bought a former potato processing plant in Penola, South Australia, that it is now converting into a $60 million milk processing plant.
On the Merrivale milk processing plant:
“Our intention is to still build in Warrnambool, but works have commenced in Penola and that is our priority at the moment,” he said.
The South Australian Government gave Midfield a $2 million grant toward the $60 million Penola project, which is close to completion.
“Penola needs to be completed, commissioned, bedded down and we need to learn how to run the plant and that is all going to come on line in the next couple of months,” Mr Aarons said.
“Penola takes precedence and then we will focus on Warrnambool,” he said.
When asked if a start on the Warrnambool plant was at least two years away, Mr Aarons said it was more likely to be 12 months.
A fenced, vacant block is what remains after the original 1940s building was demolished to make way for the apartment complex.
On the Merri St apartments:
“There is not much to say, but it is still our intention to proceed,” Mr Aarons said.
“Things are moving, things are progressing, admittedly they are progressing slowly, but they are moving”.
While potential buyers can still lodge expressions of interest with Wilson Real Estate, Mr Aarons said it was not known when construction would actually begin.
I know of at least one potential investor who lodged an expression of interest, but then heard nothing more. They have since invested elsewhere in Warrnambool.
“We haven’t confirmed a start date, but we are moving along gently, gently. It is not something we need to push quickly, but it is progressing,” Mr Aarons said.
“We have our hands full with multiple projects at the moment and we have to get a couple of key priorities out of the way.”
The former Madden’s building, once the Sandilands guest house, was demolished within weeks of the planning approval being granted for a nine-storey apartment block.
[dropcap style=”font-size: 35px; color: #8cc7d0;”] T [/dropcap]
he slow-down on the Merrivale milk plant, if it goes ahead at all, will be a sigh of relief to those who fought passionately to stop a project that would be 35m in height and operate 24 hours a day, seven days a week.
The Scott St plant, unlike the Penola plant which is several miles out of town, is in the heart of Merrivale and would be less than 100m from houses.
At the time of the approval process, the Midfield Group said the processing plant and an adjacent cold storage facility would create up to 200 jobs, but this was later wound back to 22 full time jobs.
The $70 million project received a $1.5 million grant from the former Napthine State Government and the Warrnambool City Council also sold a portion of its depot land to Midfield for the expansion.
One question I did not get time to ask the council today is how long planning permits are valid for before they need to be updated or expire?
I will let you know the answer as soon as I do.